January 30, 2015

The school board has approved the "schematic design" of the remaining facilities in the 2013 bond as they were presented by Parkhill, Smith, and Cooper at the school board special meeting. The board also approved the "design development" of the concession stand and the gymnasium. Design development of the rest of the project should be complete fro approval by March 1.

Construction documents for all existing projects will be viewed for accuracy by W.B. Kibler Construction the first 2-3 weeks of March with a 2-3 week bidding timeline that will take us into April. Projected construction on the remaining facilities should begin in late April or early May.

Tom Weeaks